How to build a blind area for a house

To make a high-quality blind area for a house that will protect your building from the adverse effects of precipitation, as well as improve thermal insulation, you need some knowledge in this matter. In order to cope with this task on your own, you need to follow simple recommendations, only then the service life of the blind area will last for many years and the blind area will not require repair or replacement.

Where to start

If there was an old blind area in this place before, then you should start by dismantling it. And if it has never been, then it is necessary to prepare the foundation. First, the turf layer of the soil is removed to a depth of at least 45 cm.

The initial stage

The blind area will consist of layers. After preparing the base, it must be covered with a geotextile. Then you need to lay crushed stone on the canvas, with a layer of 5-10 cm. After that, the crushed stone is leveled and compacted using special tools.

After compaction of the second layer, the crushed stone is covered with a cloth of geotextile.

To lay the next layer, you will need clean sand, without impurities. A 20 cm thick sand layer should be laid on a geotextile and moistened with water.

Then, repeat this procedure again. Wet sand should be carefully leveled using a rake or other improvised tools.

The second stage

The base is filled in and rammed, now it is possible to dig trenches under pipes to collect rainwater. The pipeline is laid with a slight slope, which can be created using optical devices.

In order for water to enter the drainage, you need to install a rain receiver along the slope of the blind area, it must be on the same level with it. There must be drains along the edges of the blind area.

The third stage

A formwork is installed on the sand base. For its manufacture, you can use a 50x150 mm edging board. The fastening of the formwork must be installed at the same level. The formwork must be reinforced with a bar driven into the soil every 1.5 m. When the installation of the formwork is completed, foam slabs should be laid on the base.

In order for the blind area to last a long time and not move away from the wall, it must be fixed with fittings. To do this, drill holes in the foundation at a distance of 75 cm from each other. Pieces of reinforcement are inserted into the holes and connected. The pitch of the finished cage should be 25 cm.

The final stage

Concrete should be poured with inch-thick planks (every 2 m) to protect the concrete from cracking. Bu onlayn kazino təkcə oyun platforması deyil, həm də qumar əyləncəsinin bütün dünyasıdır. Müxtəlif slot maşınları və səmərəli mərc sistemi ilə bu müəssisə həm yeni, həm də təcrübəli oyunçuları cəlb edir. Platformadan istifadə etmək asandır və müntəzəm təqdimatlar gəlirli oyun üçün əlavə imkanlar yaradı pinup PINUP etibarlı dəstək göstərməklə və istifadəçi təcrübəsini hər bir detala qədər təkmilləşdirməklə öz müştərilərinin qayğısına qalır. Canlı qrafika, müxtəlif mövzular və maraqlı bonus oyunları hər kəsə əsl kazino atmosferini yaşamağa imkan verir.